Appeal Decision 244 - Certificate of Lawful
Development.
This appeal decision summary and
assessment has been produced by Planning Jungle Limited. For more information, please go to www.planningjungle.com/?p=20
|
May 2011 - Code a00244
Summary of Case (appeal
dismissed):
The property is a two-storey
end-of-terrace house, with a hipped main roof. The application was for a proposed hip-to-gable roof extension, a
rear dormer, and three front rooflights. The proposed rear dormer would be set back by more than 20cm from the
outer edge of the section of the roof overhanging the rear wall of the house, but less than 20cm from the point
where the vertical plane of this wall meets the slope of the roof.
The key issue was whether the
proposed rear dormer would be contrary to Class B, part B.2(b), which states that “Development is permitted by
Class B subject to the following conditions … (b) other than in the case of a hip-to-gable enlargement, the edge
of the enlargement closest to the eaves of the original roof shall, so far as practicable, be not less than 20
centimetres from the eaves of the original roof”.
The Inspector stated the
following:
“The Council considers
that the proposed dormer would fall within 20cm of the eaves of the original dwellinghouse and would therefore
fail to satisfy condition B.2(b) of Class B, Part 1, Schedule 2 of the GPDO. This provides that: “other than in
the case of a hip-to-gable enlargement, the edge of the enlargement closest to the eaves of the original roof
shall, so far as practicable, be not less than 20cm from the eaves of the original roof.” The parties disagree
as to the appropriate point from which to measure the 20cm distance from the eaves required by condition
B.2(b).
The Council has submitted
a diagram indicating that the measurement should be taken from the point where the wall meets the upper part of
the roof. It draws support from an appeal decision in the London Borough of Hounslow [February 2010 - Code
a00092] where the Inspector adopted that
approach and dismissed the suggestion that the 20cm dimension should be taken from the outer edge of the eaves
commenting that: “If Parliament had wanted the measurement to be taken from the outer edge of the eaves it would
have been a simple matter to specify this.”
Since then, the Department
for Communities and Local Government has issued ‘Permitted Development for householders - Technical Guidance’ in
August 2010. The diagram on p.35 of that document specifically clarifies the position on the interpretation of
condition B.2(b) and shows the measurement being taken along the slope of the roof from the edge of the
enlargement to the outer edge of the eaves. The accompanying text states: “The measurement of 20cm should be
made along the original roof slope from the outermost edge of the eaves (the edge of the tiles or slates) to the
edge of the enlargement. Any guttering that protrudes beyond the roof slope should not be included in this
measurement.”
This is in conflict with
the conclusions of the Inspector in the Hounslow appeal decision. However, that determination pre-dates the
publication of the Technical Guidance. Although the guidance does not have statutory effect, it was commissioned
and written under a previous Government and it is designed to help understand the changes made to the GPDO by
the 2008 Amendment Order. The guidance represents a new material consideration in the interpretation of the GPDO
that was not available to the Hounslow Inspector
and his conclusions must
therefore be afforded less weight. This also applies to the two appeals in Ealing referred to in the
representations with dates respectively of January and February 2010 [January 2010 - Code
a00077 and February 2010 - Code
a00093].
The Technical Guidance clearly covers this topic in an unambiguous manner and is to be preferred and applied
to the particular facts of this case.
The submitted Drawing
1022-02 shows that the proposed dormer would be setback from the outermost edge of the eaves at the rear
and the measurement along the original rear roofslope from that point to the edge of the enlargement is
indicated to be “Approx. 400mm”. Thus, this aspect of the scheme would be in accordance with condition
B.2(b).”
The Inspector then dismissed
the appeal on the basis that the applicant had not demonstrated that the proposed rear dormer would be more than
20cm from the original side eaves.
Main
Conclusions:
·
For the purposes of the 20cm set
back, the term “eaves” applies just to the outer edge of the section of the roof overhanging the wall.
As such, the 20cm set back should be measured from the outer edge of the sloping
roof. [Note: This
would appear to contradict at least one other appeal decision – for further information see the entry in the
“Reference Section” on “B.2(b)”]. [Relevant to: B.2(b)].
Links to the “Appeal
Decision Notice” and other associated documents (e.g. drawings, etc):
·
Appeal Decision
Notice:
http://planningjungle.com/?s2member_file_download=a00244-Appeal-Decision-Notice.pdf&s2member_skip_confirmation&s2member_file_inline=yes
·
OS Map: http://planningjungle.com/?s2member_file_download=a00244-OS-Map.pdf&s2member_skip_confirmation&s2member_file_inline=yes
·
Existing
Drawings: http://planningjungle.com/?s2member_file_download=a00244-Existing-Drawings.pdf&s2member_skip_confirmation&s2member_file_inline=yes
·
Proposed
Drawings: http://planningjungle.com/?s2member_file_download=a00244-Proposed-Drawings.pdf&s2member_skip_confirmation&s2member_file_inline=yes
Download documents and diagrams of
useful
Permitted Development
information
|