Certificate of Lawful Development Appeal Decisions by category of
development.
The Town and Country Planning (General Permitted Development)
Order 1995
Part 1 (as amended on 1 October 2008)
This appeal decision summary and
assessment has been produced by Planning Jungle Limited. For more information, please go to www.planningjungle.com/?p=20
|
Applications received on or after 01/10/2008 for works that were begun prior to
01/10/2008
·
·
Where an application is received
(on or after 01/10/2008) for existing works that were begun prior to 01/10/2008, then these existing works
should be assessed against the previous Part 1 of the GPDO. [Source: January 2010 -
Code a00072].
[Source: January 2010 - Code a00075].
[Source: January 2010 - Code a00082].
[Source: January 2010 - Code a00086]. [Source: February 2010 - Code a00090]. [Source: April 2010 - Code a00117].
[Source: December 2010
- Code a00166].
·
The above conclusion applies
regardless of when the works were substantially completed. In other words, where an application is
received (on or after 01/10/2008) for existing works that were begun prior to 01/10/2008, then these existing
works (even if they were substantially completed on or after 01/10/2008) should be assessed against
the previous Part 1 of the GPDO. [Source: January 2010 - Code a00086]. [Source: December 2010 - Code a00166].
This appeal decision implies that where an application is received (on or after 01/10/2008) for existing
works that were begun prior to 01/10/2008, but which were substantially completed on or after 01/10/2008, then
these existing works should be assessed against the previous Part 1 of the
GPDO.
[Source: October 2009 - Code a00031].